Kings Worthy New Build Houses - From Concept to Completion

April 2017 – The Beginning

Works began onsite in Kings Worthy to demolish an existing bungalow.  This was to be replaced with 3 newbuild townhouses comprising Lounge, Kitchen/Family Room, WC, Bathroom, 2 Bedrooms, Study, Master Bedroom and Ensuite complete with new driveway and external landscaping.

Picture1.png

May 2017 – The Concept

CGI images were produced showing how the site would look on completion


June 2017 – September 2017 – The External Progression

Once demolition was complete works progressed to form new foundations, brick and block, roof structure and slates.


October 2017 – December 2017 – The Internal Fit Out

Internal fit out commenced with stud walls, M&E, staircases, kitchen and sanitaryware, decoration


January 2018 – March 2018 – The Finishing Touches

Final finishes began including tiling, final decorations, flooring, landscaping, paving, cedar cladding. 

To meet planning conditions a wood burning stove system was installed that provides heating to a specified zone of the houses and when in operation all water is also heated via the stove.  SAP calcs were achieved based on this system.

The external materials colour palette was chosen to compliment each other, grey aluminium window frames corresponded with roof slates.  The soffits and fascias were pre-finished in a dark grey wood effect coating, allowing for low maintenance.  Zinc cladding was added to the porch detail to also link in with the designed colour scheme. 


March 2018 - Completion